Floating Solar Power Plant- Banja reservoir

Detailed Project Design and Project Supervision of the first Floating Solar Power Plant in Albania. E.B.S shpk became part of this innovative project in which Statkraft is for the first time testing floating solar power at a hydropower plant in Albania. The project is comprised of four units of 0.5 MWp, with a total installed…

Rural Water Supply Project (IV)- Himara and Orikum

ESIA (Environmental and Social Impact Assessment), Detailed Design & Construction Supervision for “Rural Water Supply Program (RWSP) IV”, an important project of the Albanian Government, with the objective to improve and ensure sustainable access to potable water and improve wastewater infrastructure for the inhabitants and tourists of Himara Municipality and Orikum. Funding: EUR 45.15 million:…

Detailed Design for Hydropower Albania, Devoll

Detailed design for Hydropower development in some smaller catchments in Albania: Devolli upper scheme with 5 small HPP, Strelca river catchment with two small HPPs, Dunica catchment scheme with 4 small HPP, Dragostun river scheme with 4 small HPP, Zalli i Xhuxhes and Shengjini schemes with 6 small HPP, Germani river scheme with 2 small…

Design for Hydropower Development in Okshtuni River

Feasibility Study and detailed design for Hydropower development in Okshtuni River catchment Project which includes 6 HPP’ with total capacity of 31 MW. 5 of the designed HPP’s are based on runoff river flows without flow regulation. The main structures under these HPP projects consist on: Intake dam crossing the river, sedimentation tanks, pressure basins,…

Design for HPP’s of Devolli Catchment

The Devoll Hydropower Sh.A. (DHP) is an Albanian company wholly owned by the Norwegian company Statkraft AS. DHP is to develop, plan, construct and operate three hydropower plants along the Devoll river with total installed turbine capacity of approx. 278 MW, The plants will generate approximately 790 GWh/year of renewable, environmental-friendly energy. The project consists…

Supervision in Moglica HPP

Supervision of the Underground works in Moglica HPP in Joint Venture with SWECO NORGE Consulting Company. The underground works consist in about 12 Km tunnels (7 km of the tunnel is opening by drill and blast method whereas 5 km by TBM method), 1200 m derivation tunnel (Lower and upper bottom outlet tunnels), etc.